Ratios in Construction & Building
Building work is full of ratios: how much cement goes with how much sand, how steep a roof is, how a 6-meter wall fits on a sheet of paper. Here's the math behind the most common ones, with worked numbers.
1. Concrete mixes: "parts" by volume
A mix like 1 : 2 : 3 means 1 part cement, 2 parts sand, and 3 parts gravel (coarse aggregate). A "part" can be any container you like, a bucket or a shovelful, as long as you use the same one for everything. That's the whole point of a ratio: it works at any size.
| Mix (cement : sand : gravel) | Typical use |
|---|---|
| 1 : 2 : 3 | General-purpose concrete such as paths, patios, and shed bases |
| 1 : 2 : 4 | Lower-strength work such as mass fill and some foundations |
| 1 : 1.5 : 3 | A richer, stronger mix (more cement per part of aggregate) |
A higher share of cement generally gives a stronger mix. There's also a second ratio that matters just as much: water to cement. Adding extra water makes concrete easier to pour, but it weakens the result. That's why mix designs specify a water–cement ratio, often somewhere around 0.45 to 0.6 by weight.
Worked example: ordering materials for 0.5 m³ of concrete
Here's a detail that catches people out. Dry sand and gravel have air gaps between the grains, and the cement and water fill those gaps when you mix. So you need noticeably more dry material than the finished volume. Builders commonly multiply by about 1.54 to allow for this.
- Dry volume needed: 0.5 m³ × 1.54 = 0.77 m³.
- Total parts in a 1 : 2 : 3 mix: 1 + 2 + 3 = 6.
- One part: 0.77 ÷ 6 ≈ 0.128 m³.
- Cement: 1 × 0.128 = 0.128 m³. At roughly 1,440 kg per m³, that's about 185 kg, or 7 to 8 bags of 25 kg.
- Sand: 2 × 0.128 ≈ 0.26 m³.
- Gravel: 3 × 0.128 ≈ 0.39 m³.
Steps 2 to 6 are just "divide a total in a ratio," the same method as sharing money. The Three-Part Ratio Calculator will do the split for you. Most people round up and order a little extra to allow for waste.
2. Mortar for brick and block
Mortar has no gravel, so its ratios are cement : lime : sand, or simply cement : sand. Under the US standard ASTM C270, a Type N mortar (the general-purpose choice for above-grade walls) is 1 part cement : 1 part lime : 4½ to 6 parts sand by volume. Notice the sand is given as a range, which is common: the rule is that the sand should be roughly 2¼ to 3 times the combined volume of cement and lime.
Quick check: 1 + 1 = 2 parts of binder. 2 × 2¼ = 4½ and 2 × 3 = 6. That's where the 4½ to 6 range comes from.
3. Reading scale drawings
Plans are drawn to a scale such as 1 : 50 or 1 : 100. The ratio has no units, so whatever unit you measure on the paper, the real thing is 50 (or 100) times bigger in that same unit.
- Paper to real life (multiply): a wall measures 12 cm on a 1 : 50 plan. Real length = 12 × 50 = 600 cm = 6 m.
- Real life to paper (divide): a 4.2 m room drawn at 1 : 100. 420 cm ÷ 100 = 4.2 cm on the plan.
- Imperial scales: "¼ inch = 1 foot" is the same as 1 : 48, because 1 foot is 12 inches and 12 ÷ ¼ = 48.
One thing to watch: areas don't scale by the same number. At 1 : 50, a room's floor area on paper is 50 × 50 = 2,500 times smaller than in reality. There's more on this in scale drawings and maps.
4. Roof pitch
In the US, roof pitch is written as rise : run with the run fixed at 12. A 4 : 12 roof rises 4 inches for every 12 inches across. Because it's a ratio, it works in any unit: 4 feet up for every 12 feet across is the same pitch.
| Pitch | Angle | Slope as % |
|---|---|---|
| 4 : 12 | about 18.4° | 33% |
| 6 : 12 | about 26.6° | 50% |
| 12 : 12 | 45° | 100% |
Worked example: a shed roof has a horizontal run of 12 ft and a 6 : 12 pitch. The rise is 6 ft. The rafter is the hypotenuse of that triangle: √(12² + 6²) = √180 ≈ 13.4 ft, before adding any overhang.
5. Ramps and drains: slope as "1 in n"
Gentle slopes are usually written as 1 : n, meaning 1 unit of rise for every n units of horizontal run.
- Wheelchair ramps: in the US, the ADA standards set a maximum running slope of 1 : 12. To climb 24 inches, the ramp needs at least 24 × 12 = 288 inches of run, which is 24 feet. Other countries have their own rules, and many recommend gentler slopes for longer ramps.
- Drain pipes: household drains are laid with a small fall, often somewhere between 1 : 40 and 1 : 80 depending on the pipe and local rules. A 1 : 40 fall over a 10 m run drops 10 ÷ 40 = 0.25 m, or 25 cm.
A bigger number after the colon means a gentler slope. 1 : 80 is half as steep as 1 : 40.
Try it yourself
- You need 0.84 m³ of dry material for a 1 : 2 : 4 mix. How much cement, sand, and gravel is that?
- A 1 : 100 plan shows a garden that's 8.5 cm long. How long is it in real life?
- A ramp must rise 18 inches at 1 : 12. How long is its run?
Show answers
- 0.12 m³ cement, 0.24 m³ sand, 0.48 m³ gravel. 1 + 2 + 4 = 7 parts, and 0.84 ÷ 7 = 0.12 m³ per part.
- 8.5 m. 8.5 cm × 100 = 850 cm.
- 216 inches (18 feet). 18 × 12 = 216.